Many organisations have found that the PPP or PFI procurement process is best managed by dedicated professionals who have experience from previous projects, particularly if they have acted for both private and public sectors in the past, and can therefore anticipate and solve problems before they arise and with minimum fuss. At Cynergin, we have acted for either public or private sectors on numerous projects including procurement leadership roles for the Natural History Museum and the London Borough of Havering.

We are fully aware and have experience of the requirements of the various public sector investment appraisal manuals such as the HM Treasury Green Book, the NHS Estates Capital Investment Manual and the HM Treasury PFI guidance. NHS Lift and Building Schools for the Future (BSF) are of particular interest to us.

Call (+44) 0845 257 7080 (local rate from UK) for an exploratory discussion or email us now with your contact details and the nature of your enquiry and one of our specialists will call you back as soon as possible.

 

Example Performance-Based Procurement Management Service

Cynergin will provide a procurement management service for the PPP or PFI project with payment linked to the achievement of four critical milestones of a successful procurement process.

This service would comprise the following:

Phase I

  • Facilitation of definition of goals and objectives of Contracting Authority
  • Establish the Project Team
  • Define project objectives and requirements taking views of all stakeholders into account
  • Produce outline business case for approval of Contracting Authority and Government Departments (if appropriate)
  • Achieve required approvals to procure (Milestone 1)
Phase II
  • Prepare Contracting Authority for formal procurement
  • Develop tender documentation
  • Facilitate development of selection criteria and evaluation methodology
  • Prepare OJEC advertisement
  • Issue OJEC advertisement (Milestone 2)
Phase III
  • Manage competitive process
  • Brief potential bidders facilitate short-listing process
  • Brief short-listed bidders
  • Interrogate and clarify submissions for evaluation by Project Team
  • Selection of preferred bidder (Milestone 3)
Phase IV
  • Lead or participate in detailed negotiation process
  • Manage bidding process by preferred bidder(s)
  • Produce full business case for approval by relevant authroities
  • Negotiate most favourable terms/prices for Contracting Authority
  • Provide practical/technical advice on Contract terms (not specialist legal).
  • Sign Full Contracts with Bidder (Milestone 4)

Cynergin Consultants also provides experienced Project Managers who can stay with your project to provide ownership, continuity and ensure a successful contract.